视频说明
*English subtitle available*
00:00 Intro
01:30 Digging out and removing old clay material
11:11 4 days to concrete pour
11:23 Building the base before pouring – filling with gravel
27:27 FH12 rescue
30:25 Unloading material and diverting ongoing work
32:40 ? days to concrete pour
34:08 Finishing leveling of surface before insulation
37:33 Vibrator repair
41:45 Throwing on insulation before formwork
43:58 Fixing flat tire on the Caddy
45:30 2 days to concrete pour
45:39 Building concrete form and installing heating hose
57:14 Installing the rebar mesh
1:03:38 Final preparations before the concrete pour
1:07:20 10 minutes to concrete pour
1:08:04 Pouring the concrete into the form – 6.8 m³
1:11:16 Finishing concrete work
1:21:54 22 hours after pour
1:22:53 49 hours after pour
1:22:59 Removing the formwork
1:27:49 Talking about heating the driveway apron
1:29:13 Material cost for this project
1:30:34 Outro